McKinney, TX• Commercial Construction•$11M annual revenue, ~14 active projects

    McKinney General Contractor Catches a $340K WIP Reporting Error

    A McKinney commercial general contractor's monthly P&L showed strong margins. Its cash balance told a different story. We rebuilt the WIP schedule and found $340K in revenue that had been billed but not earned, hiding a margin problem on a major project.

    Anonymized composite — names, figures, and identifying details have been removed or generalized.

    Key outcomes

    • Built a percentage-of-completion WIP schedule covering all active jobs
    • Identified $340K overbilling on a single project that had hidden a 9-point margin shortfall
    • Established monthly job-cost-to-budget review meeting with operations
    • Bonding capacity increased after surety reviewed the new reports

    The challenge

    The monthly P&L showed a record year, with gross margin holding at 22%. The owner was seeing something else: payroll was getting harder to cover, suppliers were calling, and the line of credit was running short earlier each month.

    The bookkeeper closed the books monthly but didn't prepare a WIP schedule. Revenue was recorded when an invoice went out, rather than when the work was done. For long projects, that left both revenue and margin out of step with the work.

    Our approach

    We rebuilt the WIP schedule using percentage-of-completion methodology. For each of the 14 active jobs, we gathered:

    - Original contract value and approved change orders - Costs to date, including labor, materials, subs, and equipment - Estimated costs to complete, updated monthly with the project managers - Billings to date

    We used those figures to calculate earned revenue, over/underbillings, and projected gross margin by job. One large project had been billed heavily up front. It was $340K overbilled and heading toward a 13% gross margin, compared with the 22% in the original bid.

    We set up a monthly review with the controller, owner, and lead PM. They now work through each active job's WIP, cost-to-complete estimate, and remaining cash needs together.

    The outcome

    The corrected numbers were hard to hear. Year-to-date earnings were materially below what the unadjusted P&L had shown. Within a quarter, though, the owner had renegotiated the problem project's remaining scope, tightened estimates on similar work, and stopped distributing cash the business hadn't earned. Those changes paid for the work several times over.

    The surety increased the company's bonding capacity after reviewing the next year's audited financials and corrected WIP schedule. The recurring monthly cash crunch also stopped once revenue and earnings were recorded in the right periods.

    Want a similar outcome?

    Schedule a free Financial Alignment Call and we'll walk through how we'd approach your situation.

    Schedule a call
    Book a Financial Alignment CallCall